Standard Schedule Field Mappings

Acumen includes standard schedule field mappings for each of the supported platforms. You can create additional custom field mappings using the Fields tab.

Acumen Field IPMDAR Microsoft Project / Project Server Primavera P6 Primavera Risk Deltek Open Plan UN/CEFACT Safran Asta Powerproject
Activity Status Calculated Status Activity Status Calculated Progress Type Calculated NA Status
Activity Type TaskTypeID Calculated Activity Type Task Type Activity Type ProjectScheduleTask.TypeCode Calculated Type
Actual Cost NA Actual Cost Calculated Cost[Actual] Calculated NA Calculated ActualCost
Actual Duration Calculated Actual Duration Actual Duration NA NA NA Calculated ActualDuration
Actual Finish ActualFinishDate Actual Finish Actual Finish Actual Finish Actual Finish ActualScheduledBasePeriod. Finish Calculated ActualFinish
Actual Start ActualStartDate Actual Start Actual Start Actual Start Actual Start ActualScheduledBasePeriod. Start Calculated ActualStart
ACWP (AC) NA ACWP ACWP NA NA NA
Baseline Finish BaselineFinishDate Baseline Finish Planned Finish Baseline Finish Baseline Finish TargetScheduledBasePeriod. Finish Baseline Early Finish BaselineFinish
Baseline Start BaselineStartDate Baseline Start Planned Start Baseline Start Baseline Start TargetScheduledBasePeriod. Start Baseline Early Start BaselineStart
Baseline Work NA Baseline Work Budgeted Labor Units Calculated NA NA NA BaselineWork
BCWP (EV) NA BCWP BCWP (EV) Calculated Calculated NA NA NA
BCWS (PV) NA BCWS Calculated NA NA NA NA NA
Budget Cost NA Baseline Cost Calculated Cost[Budget] Calculated NA NA BudgetCost
CAM-EAC NA NA NA NA NA NA NA NA
Critical OnCriticalPath Critical Critical Critical Critical_Activity ProjectScheduleTask. CriticalPathIndicator Calculated Critical
Description Name Name Activity Name Description Activity Desc. ProjectScheduleTask.Description Description Description
EAC NA EAC EAC NA NA NA NA
Early Finish EarlyFinishDate Early Finish Early Finish Early Finish Early Finish EarliestScheduledBasePeriod. Finish NA EarlyFinish
Early Start EarlyStartDate Early Start Early Start Early Start Early Start EarliestScheduledBasePeriod. Start Early Start EarlyStart
ETC NA NA NA NA NA NA NA NA
Excluded NA IsActive NA NA NA NA NA NA
Finish CurrentFinishDate Finish Finish Finish Early Finish CurrentScheduledBasePeriod. Finish Calculated Finish
Free Float FreeFloatDuration Free Float Free Float Free Float Free Float Free Float Free Float Free Float
ID ID ID Activity ID ID Activity ID ProjectScheduleTask.Name Activity Name ID
Late Start LateStartDate Late Start Late Start Late Start Late Start Late Start Late Start LateStart
Late Finish LateFinishDate Late Finish Late Finish Late Finish Late Finish Late Finish Late Finish LateFinish
LIKELY NA NA NA NA NA NA NA NA
Longest Path OnDrivingPath Critical Longest Path Critical Critical NA Calculated Longest Path
MOD NA NA NA NA NA NA NA NA
Number of Lags Calculated Calculated Calculated Calculated Calculated ProjectScheduleTaskRelationship. LagTimeMeasure NA Calculated
Number of Leads Calculated Calculated Calculated Calculated Calculated Calculated NA Calculated
Number of FF Predecessors Calculated Calculated Calculated Calculated Calculated Calculated NA Calculated
Number of Predecessors Calculated Calculated Calculated Calculated Calculated Calculated NA Calculated
Number of SF Predecessors Calculated Calculated Calculated Calculated Calculated Calculated NA Calculated
Number of SS Predecessors Calculated Calculated Calculated Calculated Calculated Calculated NA Calculated
Number of Successors Calculated Calculated Calculated Calculated Calculated Calculated NA Calculated
Original Duration BaselineDuration (if unavailable, map to CurrentDuration) Duration Original Duration Original Duration Original Duration TotalDurationMeasure Duration
OTB NA NA NA NA NA NA NA NA
P50 Cost NA NA NA P50 Cost NA NA NA NA
P50 Finish NA NA NA P50 Finish NA NA NA NA
P50 Start NA NA NA P50 Start NA NA NA NA
P80 Cost NA NA NA P80 Cost NA NA NA NA
P80 Finish NA NA NA P80 Finish NA NA NA NA
P80 Start NA NA NA
Percent Complete CalculatedPercentComplete % Complete Calculated Percent Complete Calculated ProjectScheduleTask. CalculatedCompletionPercent NA PercentComplate
Physical % Complete PhysicalPercentComplete NA
PLAN_ACC NA NA NA NA NA NA NA NA
Primary Constraint TaskConstraints. ConstraintTypeID Constraint Type Primary Constraint Primary Constraint Calculated Primary Constraint Calculated PrimaryConstraint
Primary Constraint Date TaskConstraints. ConstraintDate Constraint Date Primary Constraint Date Primary Constraint Date Calculated Primary Constraint Date Calculated PrimaryConstraintDate
Project Finish ProjectScheduleData. CurrentFinishDate Finish Date Finish Data Date Scheduled Finish NA NA ProjectEnd
Project Start ProjectScheduleData. CurrentStartDate Start Date Start Start Project Start NA NA ProjectStart
Project Time Now ProjectScheduleData .StatusDate Status Date Data Date Finish Time Now NA NA EffectiveProgressDate
Remaining Cost NA Remaining Cost Calculated Cost[Remaining] ETC NA Calculated Remaining Cost
Remaining Duration RemainingDuration Remaining Duration Remaining Duration Remaining Duration Computed Remaining Dur. ProjectScheduleTask. RemainingDurationMeasure Remaining Duration Analyzed Remaining Duration
REPLAN NA NA NA NA NA NA NA NA
Risk Input - Duration Description NA NA NA Calculated NA NA NA NA
Risk Input - Duration LowerPcent NA NA NA Calculated NA NA NA NA
Risk Input - Duration Max NA NA NA Risk Input - Duration Maximum NA NA NA NA
Risk Input - Duration Mean NA NA NA Risk Input - Duration Mean NA NA NA NA
Risk Input - Duration Min NA NA NA Risk Input - Duration Minimum NA NA NA NA
Risk Input - Duration MostLikely NA NA NA Risk Input - Duration MostLikely NA NA NA NA
Risk Input - Duration MostlikelyPcent NA NA NA Calculated NA NA NA NA
Risk Input - Duration Notes NA NA NA Risk Input - Duration Notes NA NA NA NA
Risk Input - Duration Risk Distribution NA NA NA Calculated NA NA NA NA
Risk Input - Duration RiskFunction NA NA NA Calculated NA NA NA NA
Risk Input - Duration RiskId NA NA NA Calculated NA NA NA NA
Risk Input - Duration RiskOn NA NA NA Calculated NA NA NA NA
Risk Input - Duration Shape NA NA NA Calculated NA NA NA NA
Risk Input - Duration StdDeviation NA NA NA Calculated NA NA NA NA
Risk Input - Duration UpperPcent NA NA NA Calculated NA NA NA NA
Risk Input - Probabilistic Description NA NA NA Calculated NA NA NA NA
Risk Input - Probabilistic Notes NA NA NA Calculated NA NA NA NA
Risk Input - Probabilistic RiskFunction NA NA NA Calculated NA NA NA NA
Risk Input - Probabilistic RiskId NA NA NA Calculated NA NA NA NA
Risk Input - Probabilistic RiskOn NA NA NA Calculated NA NA NA NA
Risk Input - Probabilistic Links Description NA NA NA Calculated NA NA NA NA
Risk Input - Probabilistic Links Notes NA NA NA Risk Input - Probabilistic Links Notes NA NA NA NA
Risk Input - Probabilistic Links RiskFunction NA NA NA Calculated NA NA NA NA
Risk Input - Probabilistic Links RiskId NA NA NA Calculated NA NA NA NA
Risk Input - Probabilistic Links RiskOn NA NA NA Calculated NA NA NA NA
Risk Input - Task Existence Description NA NA NA Calculated NA NA NA NA
Risk Input - Task Existence Notes NA NA NA Risk Input - Task Existence Notes NA NA NA NA
Risk Input - Task Existence RiskFunction NA NA NA Risk Input - Task Existence Function NA NA NA NA
Risk Input - Task Existence RiskId NA NA NA Calculated NA NA NA NA
Risk Input - Task Existence RiskOn NA NA NA Calculated NA NA NA NA
Risk Input - Task Existence Probability NA NA NA Risk Input - Task Existence NA NA NA NA
Risk Output - CostSensitivity NA NA NA Risk Output - CostSensitivity NA NA NA NA
Risk Output - CostStdDeviation NA NA NA Risk Output - CostStdDeviation NA NA NA NA
Risk Output - CriticalityIndex NA NA NA Risk Output - CriticalityIndex NA NA NA NA
Risk Output - DurationCruciality NA NA NA Risk Output - Duration Cruciality NA NA NA NA
Risk Output - DurationStdDeviation NA NA NA Risk Output - DurationStdDeviation NA NA NA NA
Risk Output - DurationSensitivity NA NA NA Risk Output - DurationSensitivity NA NA NA NA
Risk Output - MeanCost NA NA NA Risk Output - MeanCost NA NA NA NA
Risk Output - MeanDuration NA NA NA Risk Output - MeanDuration NA NA NA NA
Risk Output - MeanFinish NA NA NA Risk Output - MeanFinish NA NA NA NA
Risk Output - MeanStart NA NA NA Risk Output - MeanStart NA NA NA NA
Risk Output - PercentageTaskExisted NA NA NA Risk Output - % Iterations Existed NA NA NA NA
Risk Output - ScheduleSensitivityIndex NA NA NA Risk Output - ScheduleSensitivityIndex NA NA NA NA
Schedule OBS

(Anything mapped to this field is not read in from the schedule)

OBSElementID NA NA NA NA NA NA NA
Schedule WBS

(Anything mapped to this field is not read in from the schedule)

WBSElementID NA NA NA NA NA NA NA
Secondary Constraint TaskConstraints. ConstraintTypeID NA Secondary Constraint NA Calculated Secondary Constraint Calculated SecondaryConstraint
Secondary Constraint Date TaskConstraints. ConstraintDate NA Secondary Constraint Date NA Calculated Secondary Constraint Date Calculated SecondaryConstraintDate
Start CurrentStartDate Start Start Start Early Start CurrentScheduledBasePeriod. Start Calculated Start
Total Cost NA Cost Calculated Cost[Total] Calculated NA NA TotalCost
Total Float TotalFloatDuration Total Slack Total Float TotalFinshFloat Total Float ProjectScheduleTask. TotalFloatDurationMeasure Total Float Total Float
WBS Code WBSElementID Outline Number WBS Work Breakdown Structure NA NA NA WbsCode
WBS Name NA (unless IPMDAR Cost is loaded) Outline Number WBS Name Work Breakdown Structure NA NA NA WbsName
WORST NA NA NA NA NA NA NA NA